FMP, land based

Main project parameters:

  • The plant capacity by raw materials is up to 175 tons per day
  • Espace scope of supply:  turn key project, including engineering package, main and auxiliary equipment, work on site (installation, commission)
  • Key components: Alfa Laval decanter Foodec 500, centrifugal separator, vacuum evaporation system AlfaVap, disc dryer 300 m2
  • Project status: March 2019 – finalization of commissioning.